Record Year for Connections Increases Total Renewable Capacity in the North of Scotland

Europe wind energy news_The world_s longest wind turbine blades

Read full story by clicking on this link:Record Year for Connections Increases Total Renewable Capacity in the North of Scotland to Over 4.5GW

The electricity transmission network in the north of Scotland is now supporting over 4.5GW of renewable electricity following the recent successful connections of Bienneun (Blue Energy, 108.8MW) and Bhlaraidh (SSE Renewables, 108MW) wind farms. The connection of the two wind farms, which were both delivered ahead of schedule, brings the total amount of renewable electricity connected in the north of Scotland so far this financial year to over 500MW, the highest combined capacity that has connected to the north of Scotland transmission network in a single year since privatisation.

Scottish and Southern Electricity Networks (SSEN), operating under licence as Scottish Hydro Electric Transmission Plc, owns and maintains the electricity transmission network in the north of Scotland. Under its licence, SSEN is required to develop and maintain an efficient, coordinated and economical system of electricity transmission, ensuring there is sufficient network capacity and providing a connection for developers who wish to export their generated electricity to the grid.

In advance of the imminent closure of the Renewables Obligations Scheme at the end of the financial year, there has been an increased demand for SSEN to provide connections to its transmission network for renewable developers. In response to this demand, SSEN has worked closely and collaboratively with its customers, focussed on delivering its connections to meet the specific needs and expectations of individual developers. In the case of the combined Bienneun and Bhlaraidh connection scheme, SSEN and the two developers agreed an accelerated delivery programme to ensure connection to the transmission system before changes to renewable subsidies come into effect.

Commenting, Alastair Brand, Director of Transmission Customer Connections, said:
“The demands of our customers to provide a timely connection to our transmission network have never been higher, with over 500MW of renewables already connected this financial year alone.

“I am extremely proud we have not only met the expectations and grid connection dates of the vast majority of our connection customers, in many cases we have delivered early on our commitments, providing those developers the opportunity of an earlier than expected opportunity to start exporting to the grid.

“Our network is now supporting over 4.5GW of low carbon renewable electricity, enough to comfortably power the north of Scotland and beyond when weather conditions are conducive for renewable energy.

“As we continue to grow our network to meet the needs of customers now and in the future, we will continue to place our customers at the heart of our approach to connections, building on our strong legacy as the leading GB Transmission Owner for connecting renewable projects on time.”

SSEN expects to connect a significant number of new renewable projects to its transmission network throughout the remainder of this decade, with enough contracted projects to more than double the current capacity of renewable electricity in the north of Scotland, subject to individual projects going forward.

Europe Wind energy magazine |wind power Germany Denmark Netherlands Ireland

Virginia’s Rocky Forge Wind Farm Approved

wind power US

Rocky Forge Wind Given Green Light by Virginia Department of Environmental Quality

March 2, 2017 — Charlottesville, VA — The Virginia Department of Environmental Quality (DEQ) has approved Apex Clean Energy’s “Permit by Rule” (PBR) application for the Rocky Forge Wind project, marking the first time such a project has received the statewide approval and a key milestone for Virginia’s clean energy economy.

Rocky Forge Wind is a 75-to-80-megawatt project located in a remote section of northern Botetourt County. The project will provide enough electricity to power up to 20,000 homes annually while providing $20 million to $25 million in state and local tax revenue throughout the project’s life and creating jobs during construction and beyond.

Wind energy will help drive the Virginia economy forward, especially in terms of creating great jobs,” said Mark Goodwin, president and CEO of Apex Clean Energy. “In addition to new opportunities related to the construction and operation of Rocky Forge Wind in Botetourt County, Apex employs more than 200 people today in Charlottesville. Linked with competitive pricing and clear evidence that new clean energy generation attracts major corporate investment, Rocky Forge Wind is set to begin a new chapter in Virginia’s energy future.”

The PBR process itself required more than two years of consultation and study with the DEQ and other agencies in the Secretariat of Natural Resources. The permit application covered each phase of constructing and operating Rocky Forge Wind, from pre-construction natural resource analyses to post-construction monitoring.

Rocky Forge Wind previously received unanimous approval at all levels of local permitting as well as the endorsement of the local chapter of the Sierra Club, the Virginia Deer Hunters Association, and the Virginia Conservation Legacy Fund, among other groups.

#Windpower magazine

#Wind system journal

#weekly wind power news 2017

Vestas wins 50 MW order in Norway

wind power Europe

Fortum has placed an order for 14 V126-3.45 MW turbines with Power Optimised Modes to 3.6 MW, demonstrating the competitiveness of Vestas V126-3.45 MW in the Nordic region.
Press release from Vestas Northern Europe, Malmö, Sweden, 2017-03-06 11:27 CET (GLOBE NEWSWIRE) —

The firm and unconditional order is for the Ånstadblåheia wind park in the municipality of Sortland, continuing the momentum Vestas has built in Norway. The contract includes supply and installation of the wind turbines, as well as a 5-year Active Output Management 5000 (AOM5000) service agreement. Delivery of the wind turbines is expected to begin in the third quarter of 2018.   With combined orders of close to 1,500 MW in Norway, Sweden and Finland, the V126-3.45 MW and the previous 3.0 MW and 3.3 MW rating variants are proving how the right technology can provide a strong business case in the Nordic region.

“Ånstadblåheia is an excellent wind site and yet another milestone in our strategy to expand within renewable energy. Vestas’ continuous technology development, as we see it in V126-3.45 MW’s performance, was key in our decision to choose Vestas for the project,” says Philippe Stohr, Vice President of Wind Power at Fortum.

Klaus Steen Mortensen, President at Vestas Northern Europe, adds: “Building on our good relationship from Solberg wind park in Sweden, we are proud that Fortum has again chosen Vestas and opted for our V126-3.45 MW for their Ånstadblåheia wind power plant in Norway. Vestas has the industry’s most versatile products and this project underlines our ability to provide the right technology solutions for the challenging market conditions of the Nordic region.”

Europe Wind energy magazine |wind power Germany Denmark Netherlands Ireland

Europe Wind energy magazine |wind power Germany Denmark Netherlands Ireland

Europe Wind energy magazine |wind power Germany Denmark Netherlands Ireland

Europe Wind energy magazine |wind power Germany Denmark Netherlands Ireland

Europe Wind energy magazine |wind power Germany Denmark Netherlands Ireland

Europe Wind energy magazine |wind power Germany Denmark Netherlands Ireland

Nordex strengthens its position in Ireland

thumb-1920-555599

Nordex turbines of more than 500 MW operating in the Republic of Ireland

Hamburg, 6 March 2017. The Nordex Group has passed a new milestone in the Republic of Ireland: with the commissioning of Energia Renewables’ 95 megawatt (MW) “Meenadreen” wind farm in Donegal the manufacturer passed the 500 MW mark for turbines in operation. In total, Nordex turbines with a capacity of 529 MW are now producing green power for the Irish Republic, corresponding to a market share of almost 20 percent.

In addition, in 2016 the Nordex Group improved its position in this country; with 184 MW in order intake the manufacturer approximately doubled the figure for 2015.

An example for the good development is the order for the “Slievecallan West” project received at the end of 2016. The manufacturer will be supplying 18 N90/2500 turbines for this wind farm for the Irish wind farm developer JV, Invis Energy. The turbines are to be installed on 80-metre tubular steel towers in County Clare on Ireland’s west coast. Invis Energy has also contracted the Nordex Group to service the turbines on the basis of a Premium Service contract for a period of 15 years.

“Slievecallan West” is Nordex Group’s third project with Invis Energy following the (now operational) “Knockduff” (65 MW) and “Killaveenoge” (25 MW), which is currently being commissioned.

Read all news of European industry wind news at just one click only on wind power magazine 

#Europe Wind energy magazine |#wind power  Ireland

DEME orders next generation offshore installation vessel ‘Orion’

thumb-1920-571523

‘Orion’ will feature an unrivalled combination of exceptionally high transport and load capacity, impressive lifting heights and green technology. The vessel will be built at COSCO in China and is set to be delivered in 2019.

‘Orion’ will be deployed by DEME’s subsidiary GeoSea for the construction of the largest offshore wind farms, to service the oil and gas industry and for decommissioning of offshore installations.

With a total installed capacity of 44,180 kW ‘Orion’ will be equipped with a high-tech crane with lifting capacity of 3,000 tonnes at more than 50 metres. The loads can be lifted to an unrivalled height of more than 170 m. Deck space has been maximised to provide exceptionally high transport and load capacity. The vessel can take the heaviest monopiles, jackets, wind turbine components and structures in a single shipment. With this unmatched combination of high load and lifting capacity, ‘Orion’ can transport and install the next generation of giant multi-megawatt wind turbines.

Environmental considerations have been an important element of the vessel design. ‘Orion’ has dual fuel engines and can run on natural gas (LNG). It will have a Green Passport and Clean Design notation. It will also have other environmental innovations on board, such as a waste heat recovery system that converts heat from the exhaust gasses and cooling water to electrical energy.

The 216.5 metres long Orion, featuring DP3 capability, can accommodate a crew of up to 131 people.

Luc Vandenbulcke, Managing Director GeoSea: “With ‘Orion’ we will be uniquely positioned to meet the future requirements of our customers and the trend towards larger capacity turbines and bigger wind farm projects, delivering energy at lower costs. ‘Orion’ will be capable of installing mega monopiles at greater depths. With DP3 technology the offshore installation vessel can continue operations under the most challenging conditions.”

To read more news on wind energy click on wind energy magazine

Construction finish a two wind farms on the same day

thumb-1920-425813

Wednesday the 1st of March saw the first day of spring, and the last day of erection for two wind farms. Both Tormywheel and Burton Wold South had their final rotors lifted in to place, marking the completion of the two wind farms’ construction.

Tormywheel is a 15 turbine site in West Lothian, developed by Muirhall Energy and WWS. The first towers were assembled in November 2016, however there was a short delay for blade assembly whilst waiting for the new radar mitigation for Edinburgh Airport. The radar is being built to ensure that the moving turbines are not confused with aircraft on the radar screen, a deal for which was put in place in Summer 2015 with NATS. The 15 Senvion MM92 turbines will each stand at 111 metres tall, and will have a total generating capacity of 30.75MW. The site, which was acquired by Muirhall Energy and WWS Renewables in 2015, is expected to supply over 24,000 homes once operational.

Infinergy partnered with Muirhall Energy and WWS to complete construction at Burton Wold South –  a 3 turbine extension to Burton Wold Wind Farm near Kettering in Northamptonshire. The three GE turbines have a rated power of 2.75MW , are 135m to tip and use a 120m rotor.

Western Plains Wind Farm boosts Westar’s emission-free electricity to more than 50%.

thumb-1920-460065

To read full story click here:Half of electricity serving homes and businesses met through renewables, Wolf Creek.

March 1, 2017

Westar Energy’s new Western Plains Wind Farm near Spearville is now complete, advancing Kansas’ position as a leading producer of renewable energy. With energy production from Western Plains Wind Farm, Westar Energy can now meet more than half the annual electricity needs of the homes, businesses and organizations it serves with no emissions.

“By carefully selecting the locations for our wind farms, we’ve cost-effectively grown our commitment to renewable energy,” John Bridson, senior vice president, generation and marketing, said. “In February, on a day with particularly windy conditions, there was one hour where we met 90 percent of our customers’ electricity needs with renewable energy.”

The Western Plains 280 megawatt wind farm in Ford County began full operation March 1. Westar will own and operate the wind farm, which Infinity Wind developed and Mortenson Construction built. Westar selected Siemens turbines. Nacelles, the key component housing the electric generators for the turbines, were manufactured in Hutchinson.

Over the next 20 years of operation about $75 million in land lease payments and payments to local and county government will boost the local economy. Construction entailed about 200 temporary jobs, and the wind farm brings about three dozen permanent jobs to the community.

Western Plains is the third wind farm owned by Westar Energy, in addition to eight wind farms and a land fill gas generator that Westar makes possible through long-term power contracts. Later this spring, Westar will add a 1 MW community solar installation in South Hutchinson to its renewable commitment. Renewable sources meet about a third the annual electricity needs of the homes, businesses and organizations served by Westar, with Wolf Creek Nuclear Generating Station providing another 20 percent.

Europe Wind energy magazine|Senvion wins major contract in the UK

wind power 1Senvion wins major contract in the UK with Banks Renewables

Contracts for over 151 megawatts for three onshore wind farms

Senvion, a leading global manufacturer of wind turbines, has concluded contracts with Banks Renewables for the supply and installation of 47 turbines for three wind farm projects totalling 151 megawatts (MW). Senvion has also signed 20 year operations and maintenance contracts for all three projects.

Senvion will supply 26 of its 3.4M104 turbines for Kype Muir Wind Farm, located in South Lanarkshire, Scotland. The wind farm will have a total rated output of 88 megawatts and will produce enough electricity to power 62,000 homes each year. The wind farm is expected to come online at the start of 2019.

Also located in South Lanarkshire, the Middle Muir Wind Farm will consist of 15 Senvion 3.4M114 turbines, eight at 79 meter hub height and seven at 93 meter hub height. These hub heights will enable the wind farm to take full advantage of variable wind speeds. The wind farm will have a total rated output of 51 megawatts and will produce enough electricity to power over 33,000 homes. Middle Muir is scheduled to go live in 2018.

Located near Darlington in North East England, Moor House Wind Farm will consist of six Senvion MM100 turbines at a total rated output of 12 megawatts and will produce sufficient energy to power 9000 homes. Delivery will start in August 2017 and commissioning is expected to be completed early in 2018.

The three wind farms were all successful in the UK government’s first competitive Contracts for Difference (CfD) programme for onshore and offshore projects in 2015.

Jürgen Geissinger, CEO of Senvion, said: “The successful conclusion of these three contracts continues the positive start to 2017 for Senvion. These orders also demonstrate that Senvion provides a strong product fit to match the market requirements and wind conditions in the UK.”

Guy Madgwick, Managing Director of Senvion Northern Europe, said: “We are delighted to be continuing our successful partnership with Banks Renewables. We look forward to building on this relationship through 2017 and beyond.”

Richard Dunkley, Managing Director at Banks Renewables, added: “We have enjoyed a long and successful relationship with Senvion. We are very pleased to be able to utilise their high quality turbines and expert support services once again for these three landmark projects. Onshore wind in general and these projects in particular represent the best value for money to consumers as the government seeks to deliver on its climate change obligations, and it’s exciting to now be accelerating the process of taking these wind farms forward.”

#Europe Wind energy magazine |#wind power Germany Denmark Netherlands Ireland

Wind power|Senvion signs order for over 300 MW in Australia news

wind-turbines

Senvion signs order for over 300 MW in Australia ,read full story on wind power magazine
Global expansion strategy continues successfully

Senvion, a leading global manufacturer of wind turbines, has signed a conditional contract with Nexif Energy for the EPC contracts and maintenance agreements for the 25 turbine Glen Innes Wind Farm in New South Wales and the 59 turbine Lincoln Gap Wind Farm in South Australia.

Jürgen Geissinger, CEO of Senvion, said: “We are particularly happy to announce this contract with Nexif Energy, only a short time after being selected as single preferred supplier. This highlights the strong product fit Senvion can provide for Australian projects. We are very much looking forward to further building on our partnership with Nexif Energy.”

Both wind farms will see the introduction of the new Senvion 3.6M140 turbine into the Australian market. Compared to its predecessor, the energy yield has been increased by up to 20 per cent at wind speeds of 7.5 m/s, and the lifetime has been extended by 25 per cent from 20 to 25 years. Improvements to the blades have resulted in lower sound in all operating modes. Combined, the projects will deliver over 300 megawatts (MW) of clean, renewable energy to Australian consumers.

Raymond Gilfedder, CEO and Managing Director of Senvion Australia said: “The next few years will be a busy time for the wind industry in Australia. Senvion is in an excellent position to contribute to Australia’s clean energy future with a great range of turbines and an experienced and professional team. The 3.6M140 turbine is particularly well suited to the Australian market delivering exceptional value to our customers.”

Raymond Gilfedder joined the Senvion Australia team recently as CEO and Managing Director after having been Managing Director for Senvion’s Northern Europe hub since 2013.

Since commencing operations in Australia in 2002, Senvion has installed 218 wind turbines from across the Senvion two megawatt series with a cumulated rated power of over 440 MW in Australia. Senvion Australia Pty. Ltd. is the regional subsidiary providing Senvion wind turbine technology and solutions across Australia, New Zealand and the Southern Pacific region.

Wind energy industry Australia| Wind power Australasia news

Europe Wind energy magazine post|SgurrEnergy supports JP Morgan

istock_000022136935_full-002-768x508

SgurrEnergy, part of Wood Group’s clean energy business, recently supported JP Morgan Asset Management as technical and commercial adviser on the acquisition of the Terra Firma UK onshore wind farm portfolio.

The portfolio is one of the UK’s largest onshore wind portfolios, comprising 343MW of installed capacity across 19 sites, in addition to a 66MW project that is expected to be online later this month.

As part of the scope of work, SgurrEnergy’s engineers and consultants provided comprehensive due diligence combined with SgurrOptimiser techniques to assess the potential for improving output, reducing Opex and extending asset life across the portfolio of wind projects.

David Cunningham, Principal Financial Analyst at SgurrEnergy, said: “Our ability to understand and characterise wind and its relationship with the turbine allows for a full assessment of where we can provide effective solutions to improve financial returns for investors.

“By using SgurrOptimiser, investors are made aware at an earlier stage where the risks are and what returns can be made, allowing them to bid more effectively.”

#Europe Wind energy magazine #wind power Germany # wind power Denmark # wind power Netherlands # wind power Ireland